This Week (June 15 to June 19): Storm sewer work was completed between East Washington Street and West Pine Street. The roadway crew completed excavation and placement of new road base from the Finnegan Lake Road intersection through the western project limit.
Next Week (June 22 to June 26): Storm sewer work will be completed in the West Pine Street intersection and the pipe crew will work north toward Cedar Street. The grading crew will begin roadway excavation and base placement near the East Main Street intersection working north. Landscaping crews will restore ditches on the west end of the project from Harding Avenue to the west.
Detour: WIS 22 will remain closed and detoured. The project detour route continues to use County H and County R. This detour has been temporarily removed. A new detour has been established, directing WIS 22 traffic to use County BE, County E, and WIS 32. The new detour will remain in-place until June 30. At that point, the original detour using County H & County R will be reset.